2019 Haseltine Street (Sheldon to East Street) Utility Construction Schedule:
Generally, the order of operations discussed at the 5/15 preconstruction meeting are as follows:
- Detour signage installation
- Pulverize road surface
- Install Sanitary sewer main (Sheldon to Ira)
- Replace water valves and fittings (Sheldon to Ira)
- Install sanitary and water services (Sheldon to Ira)
- J&J to start storm sewer installation and street grading (Sheldon to Ira)
- Gerke to complete East Haseltine utility work between Ira and East Street in same order as above.
- The Gerke contract will complete the water main drilling on Ithaca Road
- Meanwhile, J&J will continue to the east.
As of the 5/15 precon meeting, items 1& 2 were going to happen late the week of 6/10 with Gerke’s crew starting June 19th. Gerke’s utility contract work is to be complete by early August. J&J Underground will start the storm sewer early to mid-July and complete the street work sometime in October.