Haseltine Street Reconstruction Project (Sheldon to East Streets) 2019

2019 Haseltine Street (Sheldon to East Street) Utility Construction Schedule:

Generally, the order of operations discussed at the 5/15 preconstruction meeting are as follows:

  1. Detour signage installation
  2. Pulverize road surface
  3. Install Sanitary sewer main (Sheldon to Ira)
  4. Replace water valves and fittings (Sheldon to Ira)
  5. Install sanitary and water services (Sheldon to Ira)
  6. J&J to start storm sewer installation and street grading (Sheldon to Ira)
  7. Gerke to complete East Haseltine utility work between  Ira and East Street in same order as above.
  8. The Gerke contract will complete the water main drilling on Ithaca Road
  9. Meanwhile, J&J will continue to the east.

As of the 5/15 precon meeting, items 1& 2 were going to happen late the week of 6/10 with Gerke’s crew starting June 19th.   Gerke’s utility contract work is to be complete by early August.  J&J Underground will start the storm sewer early to mid-July and complete the street work sometime in October.