Haseltine Street Reconstruction Project Information

May 1, 2018

Haseltine Street Construction Notice:

Beginning in June, the City of Richland Center will begin the Haseltine Street Reconstruction project. The project includes street and utility replacement on Haseltine Street from Main Street to Sheldon Street. The street construction will include removing the existing street and installing new sanitary sewer, water main, storm sewer, base course, curb and gutter, asphalt pavement, and driveway aprons.

During construction, the road will be open to local traffic only. However, local residents will have limited access to driveways at times during the project. Mail delivery will be maintained throughout the project.

Below is an approximate construction schedule for the street and utility construction. The construction schedule may change due to weather or other construction delays.

  • Utility Contract (Sanitary Sewer and Water Main Replacement)
    • Start Construction – June 4, 2018
    • Final Completion – August 10, 2018
  • City Contract (Storm Sewer and Street Construction)
    • Start Construction – July 20, 2018
    • Final Completion – September 28th 2018

Gerke Excavating is the contractor for the street construction and Vierbicher Associates are the engineers for the project. If you have any questions contact Matt Muchow from Vierbicher at 608-434-1053.

Thank you,

City of Richland Center

Vierbicher Associates

 