10/8/2018 Construction Update

Haseltine Street:  The street and storm sewer construction on the project was finished last week.  Gerke will have a seeding crew come in this week to finish restoration on the project.   

 Gerke is bringing in the equipment this week to complete the Mr. Manhole adjustments on the sanitary manholes.

 

Westside Drive Reconstruction:   All the underground utilities are complete on the project.  Gerke has approximately 1 more day of street removals and base aggregate at the north end of Westside Drive.  They are not building the road today due to the rain.

 Augelli Concrete plans to come today to start setting up stringline for the remaining curb on the project.  If they do not get delayed with rain, they are planning to do the remaining curb and gutter on the project this Friday or Saturday.  

The current schedule is to complete the remaining asphalt on the project the week of October 22.

 

Panorama Estates:   Gerke Excavating now has base aggregate on the entire road.  Assuming they do not get further delayed with rain, Augelli Concrete is planning to do the curb and gutter on the project this Friday or Saturday.  

 The asphalt on the west side of USH 14 was completed last week.  After the asphalt was complete, Gerke modified the traffic control so they can start the median construction on the east end of the project today.

 

 