Haseltine Street:   Gerke has completed the punch list items on the project.  The lawn restoration will be monitored in the spring to make sure the grass has established.  There will be one final pay request on the project that includes the rest of the street construction.


Westside Drive Reconstruction:  Gasser has been on site paving Westside Drive the last two days.  They plan to have almost all the asphalt done by the end of the day today, except for a small amount at the north end of the project.  Their goal is to finish the remaining asphalt on the project on Saturday.  Depending on weather or other delays, the asphalt driveways might not be finished until early next week.

Augelli Concrete plans to come back on Monday after Gasser is out of the way to finish the remaining concrete driveways and steps on the project.  

 In addition to the asphalt and concrete, Gerke will be finishing the lawn restoration, retaining wall, and Mr. Manhole adjustments after the asphalt is finished.  

 


Panorama Estates:  Gasser was on site today finish grading the road in preparation of paving tomorrow.  Gasser plans to pave the road tomorrow and the asphalt trail on Saturday.  

Augelli Concrete plans to come on Monday to finish the remaining concrete sidewalk on the project.  

 Century Fence was on site today doing the pavement marking on USH 14.  The intersection improvements are now complete, except for some concrete sidewalk at the intersection and lawn restoration.

 